1. Facility Reception, Weighing and Unloading
- Weighing and Radiation Control: Waste trucks arriving on site pass over the weighbridge; their weight is recorded and they are simultaneously scanned by radiation control panels.
- Reception Bunker / Tipping Floor: Waste is discharged into an enclosed waste bunker operating under negative pressure (preventing odour escape) or onto the reception platform.
- Coarse Sorting: Crane operators or machinery visually identify and remove very bulky materials (concrete blocks, engine blocks and large metal parts) that could damage the combustion system and crushers.